Your home, A-0801
3 BHK · 1,050 sq ft carpet · east-facing corner · booked 18 March 2026 · possession promised December 2026.
Where the building has reached
Surveyed 10 Aug 2026Updates from the site
Structure visible to the 20th floor
Monthly aerial survey completed. Slab work has progressed two floors since July. Against the December 2026 date, structure is on schedule; finishing is the stage to watch.
Plumbing rough-in started, floors 1–10
Astral CPVC as specified in your agreement. Delivery invoice checked against the specification — it matches. Copy filed under Documents.
Slab work complete to floor 16
Your floor is cast. This milestone triggered the 40% payment stage — see Money.
What goes into your home
Your agreement includes a standard specification. Anything above it is priced here, before you commit to it — never discovered on a bill afterwards.
Every selection is within your standard allowance.
Bathroom fittings
Choose by 30 Sep 2026After this date the standard option is installed and changes become site rework, which costs more and delays your floor.
Bedroom flooring
Choose by 31 Oct 2026Kitchen platform
Choose by 31 Oct 2026False ceiling
Choose by 15 Nov 2026Every rupee, both directions
Everything with your name on it
One place, downloadable, permanent. You keep access after possession.
| Document | Reference | Dated | State |
|---|---|---|---|
| Allotment letter | AH/A-0801/2026 | 18 Mar 2026 | On file |
| Agreement for sale | NGP-3/4471/2026 | 02 Apr 2026 | Registered |
| Stamp duty challan | MH004471202601 | 02 Apr 2026 | On file |
| Payment receipts (5) | AH-0412 … AH-0702 | Ongoing | On file |
| Approved floor plan, A-0801 | NMC/BP/2023/1190 | 28 Mar 2023 | On file |
| Specification annexure | Schedule C | 02 Apr 2026 | On file |
| CPVC supply invoice | AST/2026/22841 | 26 Jul 2026 | Matches spec |
| Occupancy certificate | — | — | At completion |
| Possession letter | — | — | At handover |
Tower A, before you move in
41 of 56 homes booked · 33 families here
Saw the August drone survey. Slab work to 16 is done, which means our floor is cast. Genuinely didn't expect to be able to check that from Pune.
Started a poll on parking allocation — first-come-first-served versus by unit size. 28 of 33 have voted so far. Please add yours before Friday.